Free PMP Exam Sample Question

Question:

During which project management process will you manage procurement relationships and monitor contract performance?

A. Conduct Procurements11954322131712176739question mark naught101 02.svg.med
B. Control Procurements
C. Close Procurements
D. Plan Procurement Management

-------------------------

HINT: This must be a process from the Monitoring and Controlling Process Group.

-------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

Answer and Explanation:

The Correct Answer is B.

As you want to manage the procurement relationships and monitor control performance, this must be a process from the Monitoring and Controlling process group. Control Procurements is the process of managing procurement relationships, monitoring contract performance, and making changes and corrections as needed. "Control Procurements" is the correct answer to this question.

 