Free QuestionQuestion:

Which of the following techniques can help in controlling project risks?

A. Quality Audit
B. Pareto Diagram
C. How-How Diagram
D. Reserve Analysis

-------------------------

HINT: Consider the tools and techniques for the Control Risks process.

-------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

Answer and Explanation:

The Correct Answer is D.

Reserve analysis, risk audits and status meetings are all tools and techniques of the Control Risks process.