Free PMP Exam Sample QuestionQuestion:

You are managing a hotel construction project. You are doing great in terms of the project schedule but you have a gut feeling that you might be over budget. You ask your project team to calculate the current project performance measurements. Your project TCPI based on BAC is 0.9. Which of the following is true regarding your project's current situation reflected by this TCPI value?

A. You are within your budget
B. You are over budget
C. You are behind schedule
D. You are ahead of schedule

-------------------------

HINT: TCPI is not a schedule performance measurement.

-------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

Answer and Explanation:

The Correct Answer is A.

TCPI is not a schedule performance measurement. When you are looking at the TCPI for a project, a higher number means it's time to take a stricter cost management approach. When the number is < 1.0, you are well within your budget and you can relax a bit.

 