Free PMP Exam Sample Question

Free PMP Exam Sample QuestionQuestion:

You are managing a process improvement project for your organization. During the Perform Quantitative Risk Analysis process you identified that there are some risk categories missing in your Risk Breakdown Structure (RBS). You need to document these new risk categories in your RBS. What is the best way to do this?

A. Revisit the Plan Risk Management process to update the RBS
B. Revisit the Identify Risks process to update the RBS
C. Revisit the Perform Qualitative Risk Analysis process to update the RBS
D. Update the RBS in the Perform Quantitative Risk Analysis process

-------------------------

Hint: The RBS is a hierarchically-organized depiction of the identified project risks, arranged by risk category and subcategory that identifies the various areas and causes of potential risks.

-------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

Answer and Explanation:

The Correct Answer is A.

The RBS is a hierarchically-organized depiction of the identified project risks arranged by risk category and subcategory that identifies the various areas and causes of potential risks. The RBS is part of the Risk Management Plan, and updating it means revisiting the Plan Risk Management process.

 