Free PMP Exam Sample Question

The following PMP® exam sample question is taken from the Free PMP Exam Simulator (The answer is at the very bottom):

------------------------------

You are currently performing planning for a construction project. Your project sponsor asks you to send him your project's Resource Breakdown Structure so that he can present it to his senior management during an upcoming meeting. You have not yet developed the Resource Breakdown Structure for your project. Which process do you need to start in order to develop it?

A) Estimate Activity Resources
B) Plan Human Resource Management
C) Develop Project Management Plan
D) Acquire Project Team

------------------------------

Hint: The Resource Breakdown Structure is a hierarchical structure of the identified resources broken down by resource category and resource type.

------------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

Answer and Explanation:
The Correct Answer is A. The Resource Breakdown structure (RBS) is a hierarchical structure of the identified resources, broken down by resource category and resource type. The RBS is developed during the Estimate Activity Resources process.