Mary is managing a data migration project. The project is in execution. The project’s current total Earned Value (EV) is $25,000 and the current Schedule Variance (SV) is $5,000. What is the project’s current Schedule Performance Index (SPI)?

A) 1
B) 1.25
C) 0.83
D) 0.2

------------------------------

Hint: You need 2 formulas to calculate the correct result.

------------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

Answer and Explanation:
The Correct Answer is B. SPI = EV/PV. We know that EV = $25,000, but not the PV. This means we first have to determine the current PV in order to determine the current SPI.