Free PMP Exam Sample Question

Free PMP Exam Sample QuestionThe following PMP® exam sample question is taken from the Free PMP Exam Simulator (The answer is at the very bottom):

------------------------------

To calculate the total project cost, you use a technique that uses input values selected at random from probability distribution of possible cost. Which of the following options best describes this method?

A) Automated Schedule Development
B) Monte Carlo Analysis
C) Schedule Risk Analysis
D) e-Pert

------------------------------
Hint: This is a simulation technique.
------------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

Answer and Explanation:
The Correct Answer is B. Monte Carlo analysis is a simulation technique. It uses computer models and estimates of risk usually expressed as a probability distribution of possible costs or durations at a detailed work level.