You are performing Earned Value Management on your project. The Cost Performance Baseline in Earned Value Management is also a part of:
 

A.) Cost Estimating Baseline
B.) Performance Measurement Baseline
C.) Cost Measurement Baseline
D.) Budget Baseline

------------------------------

Hint: The keyword to look here is 'performance'.

-----------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

ANSWER AND EXPLANATION:
The correct answer is B
Explanation: A Cost Performance Baseline is a part of the Performance Measurement Baseline. The Performance Measurement Baseline is an approved plan for the project work to which the project execution is compared, and deviations are measured for management control. The Performance Measurement Baseline typically integrates the scope, schedule and cost parameters of a project.
Reference: PMBOK® Guide 4th Edition, pages 178, 267