You are managing a construction project for a client and have subcontracted out some of the project work. You negotiated different contracts with the subcontractors, which include various activities and resources, such as site excavation, raw material supplies, and labor workforce to different subcontractors. Each of these contract life cycles can end during which phase of your project life cycle?

A.) The Closing phase of the project life cycle.
B.) The Executing phase of the project life cycle.
C.) the Monitoring and Controlling phase of the project.
D.) Each contract life cycle can end during any project life cycle phase.

------------------------------

Hint: The life span of a contract life cycle depends upon the nature of the work involved not on the entire project work.

------------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

ANSWER AND EXPLANATION:
The correct answer is D
Explanation: A complex project can involve managing multiple contracts or subcontracts simultaneously or in sequence. In such cases, each contract life cycle can end during any phase of the project life cycle. The buyer-seller relationship can exist at many levels on any one project and between organizations internal to and external to the acquiring organization.
Reference: PMBOK® Guide 4th Edition, page 315