You are managing an amusement park development project. You received the following estimates for site excavation and area development activity, which are critical to the success of your project. The most likely estimate is $100,000, the optimistic estimate is $90,000, and the pessimistic estimate is $120,000. What is the variance of the data?

A.) $25,000,000
B.) $5,000
C.) $30,000
D.) $10,5000

------------------------------

Hint: Calculate the standard deviation using the PERT method and then calculate the variance from it.

------------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

ANSWER AND EXPLANATION:
The correct answer is A
Explanation: The standard deviation can be calculated as (Pessimistic - Optimistic) / 6. Variance can be calculated by squaring the standard deviation. For the given data, the variance is $25,000,000 and the standard deviation is $5,000. Note: Whenever any question asks about weighted average, standard deviation or the variance from given three estimates, always use PERT formulas to compute the required calculations. This needs to be done even if the question doesn't explicitly tell you to use PERT formulas.
Reference: PMP Study Guide 5th Edition (Sybex), page 170