The following PMP® exam sample question is taken from the Free PMP Exam Simulator:

------------------------------

The majority of effort in the project Time Management knowledge area will occur in which of the following processes while you are executing the project?

A.) Control Schedule
B.) Develop Schedule
C.) Estimate Activity Resources
D.) Estimate Activity Durations

------------------------------
Hint: Project Execution and project Monitoring & Control are the two process groups that require the most effort.

------------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

ANSWER AND EXPLANATION:
The correct answer is A
Explanation: As the project activities are being performed, the majority of effort in the project Time Management knowledge area will occur in the Control Schedule process to ensure completion of project work in a timely manner.
Reference: PMBOK® Guide 4th Edition, page 130