You have finished estimating costs for your project. What is your next activity to manage the costs?

A.) Develop Cost Performance Baseline
B.) Develop Work Performance Measurements
C.) Develop Budget Forecasts
D.) Plan Quality

------------------------------

Hint: Determine Budget is the immediate process after the Estimate Costs process.

------------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

ANSWER AND EXPLANATION:
The correct answer is A
Explanation: The immediate activity following estimation of costs is determining the budget. The output of the Determine Budget process is the development of a Cost Performance Baseline.
Reference: PMBOK® Guide 4th Edition, page 167