Free PMP Exam Sample Question

The following PMP® exam sample question is taken from the Free PMP Exam Simulator:

------------------------------

An element of a Work Breakdown Structure that can be viewed at the lowest level of each branch is referred to as which of the following?

A.) Control Account
B.) Work Breakdown Structure Component
C.) Work Package
D.) Task

------------------------------
Hint: A work package is at the lowest level of a WBS.

------------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

ANSWER AND EXPLANATION:
The correct answer is B C

Explanation: A Control Account is a management control point where scope, budget, resources, actual cost and schedule are integrated and compared to earned value for performance measurement. Control accounts are placed at selected management points (specific components at selected levels) of the Work Breakdown Structure. A Work Package is a deliverable or project work component at the lowest level of each branch of the Work Breakdown Structure. Tasks are the results of further decomposition of work packages.

Reference: PMBOK® Guide 5th Edition, page 126