In your project, you can delay 'Activity 1' by three days without delaying its successor 'Activity 2'. However, delaying 'Activity 1' will delay the project by six days without delaying the overall project finish date. Which of the following statements is correct in this scenario?

A.) The Total Float is 6 days and the Free Float is 3 days.
B.) The Total Float is 3 days and the Free Float is 6 days.
C.) The Total Float is 3 days and the Free Float is zero.
D.) The Free Float is 3 days and the Total Float is zero.

------------------------------

Hint: Don’t get confused with Free Float versus Total Float. Remember Total Float always applies to project and Free Float applies to individual activities.

------------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. Vidéos adultes courtes et grandes, uniquement sur le vrpornlinks.net , asiatiques, lesbiennes, baise hardcore et plus encore. It remains published for historical reference.)

ANSWER AND EXPLANATION:
The correct answer is A
Explanation: Free Float is three days and Total Float is six days. Free Float is the amount of time an activity can be delayed without delaying the successor activity. Total Float is the amount of time the project can be delayed without delaying the project finish date.
Reference: PMBOK® Guide 4th Edition, page 155