Free PMP Exam Sample Question

The following PMP® exam sample question is taken from the Free PMP Exam Simulator at http://free.pm-exam-simulator.com:

------------------------------

Maintaining a realistic project schedule is very important for the successful execution of a project. When you develop a schedule, which of the following items from the Project Scope Statement will impact the schedule?

A.) Work Packages
B.) Activity List
C.) Assumptions and Constraints
D.) Activity Attributes

------------------------------

Hint: Think about different parts of the Project Scope Statement.

------------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

Please click here for the correct answer and explanation.