Free PMP® Exam Sample Question

Free PMP® Exam Sample QuestionA multiphase project that has been executed with internal resources has reached a phase gate. The key project stakeholders want to determine if the phase has met its success criteria, and whether or not the project should progress to the next phase. In addition to the project management plan, which documents will be required?

A. Risk register and risk report
B. Lessons learned register and lessons learned repository
C. Business documents and project charter
D. Agreements including procurement contracts
--------------------
HINT: Which documents provide relevant information to decide the continued viability of the project before starting the next phase?
--------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

Answer and Explanation
The correct answer is C.

A phase gate is a review point at the end of a phase to determine if the project will continue to the succeeding phase, end the project, repeat the phrase, or continue with some modifications. The business documents and project charter are needed to determine whether or not the project should progress to the next phase. The project charter will provide the project's success criteria. The business documents include the business case and benefits management plan. The business case documents the business need and the cost-benefit analysis that justifies the project. The benefits management plan is used to measure whether the benefits of the project are being achieved as planned. The project management plan, project chart, and business documents are all needed to assess the continued viability of a project.

A. Risk register and risk report
Incorrect. A phase gate is a review point where the continued viability of the project is assessed before entering the next phase. The risk register and risk report do not provide insight into the project's business objectives to compare with project performance to decide the future of the project.

B. Lessons learned register and lessons learned repository
Incorrect. The continued viability of a project is assessed at a phase gate. An understanding of project performance against business objectives is necessary to conduct the review, and the lessons learned register and lessons learned repository are not the best sources of this information.

C. Business documents and project charter
Correct. The business documents and project charter are needed to determine whether or not the project should progress to the next phase. The project charter will provide the project's success criteria. The business documents include the business case and benefits management plan. The business case documents the business need and the cost-benefit analysis that justifies the project. The benefits management plan is used to measure whether the benefits of the project are being achieved as planned.

D. Agreements including procurement contracts
Incorrect. The question states that the project is being conducted internally. Therefore, there are no procurement contracts associated with the project, and this answer choice can be eliminated as a correct response.

Reference: A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) 21, 124-125