Free PMP Exam Sample Question

QandA11Question:

You are managing a telecommunications network deployment project. You are employed by a telecom equipment company that specializes in installing and implementing the telecom equipment for this project. Since your company is not experienced in civil works, you have outsourced all of the civil works activities to an outside contractor. You are now finalizing all of the open claims with this contractor. Which project management process are you currently performing?

A. Close Procurements
B. Close Project or Phase
C. Control Procurements
D. Validate Scope

-------------------------

HINT: Which project management process involves administrative activities such as finalizing open claims, updating records to reflect final results, and archiving such information for future use?

-------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

Answer and Explanation:

The Correct Answer is A.

The Close Procurements process also involves administrative activities such as finalizing open claims, updating records to reflect final results, and archiving such information for future use. Close Procurements addresses each contract applicable to the project or a project phase.

 