Free PMP Exam Sample Question

Question:

You are managing a construction project and your project budget is $20,000. You have spent $17,000 so far and the project is 75% complete. A new project budget of $25,000 has been approved. What should your cost performance be if you want to complete your project within the new approved budget?

A. 1.667
B. 0.882
C. 0.625
D. 0.521

-------------------------

HINT: Calculate the TCPI based on EAC.

-------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

Answer and Explanation:

The Correct Answer is C.

Since the BAC = $20,000 and the project is 75% complete, the EV = (BAC x % complete) = $15,000. Now you need to calculate your desired future cost performance, you should calculate the TCPI based on EAC by using the formula TCPI = (BAC-EV)/(EAC-AC) = (20,000 - 15,000) / (25,000 - 17,000) = 5,000/8,000 = 0.625.

Print Email