Free PMP Exam Sample Question

Free PMP Exam Sample QuestionQuestion:

You are managing a website development project and have just calculated your project performance measurements. Your project CPI is 0.9 while your project SPI is 1.1. Which of the following statements is correct regarding your project's current situation?

A. You are over budget and ahead of schedule
B. You are under budget and behind schedule
C. You are over budget and behind schedule
D. You are under budget and ahead of schedule

-------------------------

HINT: SPI=EV/PV while CPI=EV/AC.

-------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

Answer and Explanation:

The Correct Answer is A.

An SPI greater than 1.0 indicates that more work was completed than was planned, while a CPI value less than 1.0 indicates a cost overrun for work completed. Since your CPI is 0.9 and SPI is 1.1, you are over budget but ahead of schedule.

 