Free PMP Exam Sample Question

 

Free PMP Exam Sample QuestionQuestion:

Which of the following performance metrics measures project performance against the project scope?

A. Schedule Performance Index
B. Cost Performance Index
C. Cost Variance
D. No metric is used

-------------------------

HINT: SPI is Schedule Performance Index, CPI is Cost Performance Index.

-------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

Answer and Explanation:

The Correct Answer is D.

SPI is Schedule Performance Index, CPI is Cost Performance Index. None of these metrics measure the project performance against the project scope.
In fact, there is no metric mentioned whatsoever in the PMBOK® Guide that measures this kind of performance. The performance can be measured against the scope baseline but there is no metric for doing so. The question is trying to trick you.

 