Free PMP Exam Sample Question

 

Free PMP Exam Sample QuestionQuestion:

The Change Control Board reviews all of the change requests for every project in your company. This board follows all the recommended activities outlined in the PMBOK® Guide . Based on this scenario, which of the following would not be performed by the Change Control Board?

A. Documenting change request decisions and recommendations
B. Reviewing change requests
C. Creating change requests
D. Accepting or rejecting change requests

-------------------------

HINT: What specific functions does the Change Control Board perform according to the PMBOK® Guide ?

-------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

Answer and Explanation:

The Correct Answer is C.

According to the PMBOK® Guide , the Change Control Board is responsible for reviewing, evaluating, approving, delaying, or rejecting changes to a project, with all decisions and recommendations being recorded. It is up to the individual project team members to actually create the change requests.

 