Free PMP Exam Sample QuestionQuestion:

You are the project manager of a process improvement project for a factory operation. Which of the following activities will not be performed during the Monitor and Control Project Work process of your project?

A. Comparing actual project performance against the Project Management Plan
B. Identifying new risks and analyzing, tracking and monitoring existing project risks
C. Analyzing change requests and either approving or rejecting them
D. Monitoring implementation of approved changes as they occur

-------------------------

HINT: Monitor and Control Project Work is the process of tracking, reviewing and regulating the progress to meet the performance objectives defined in the Project Management Plan.

-------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

Answer and Explanation:

The Correct Answer is C.

Comparing actual project performance against the Project Management Plan, identifying new risks, analyzing, tracking and monitoring existing project risks and monitoring the implementation of approved changes are all activities that you need to perform during the Monitor and Control Project Work process. However, you will not review change requests during this process since this needs to be done during the Perform Integrated Change Control process.

 