Free PMP Exam Sample Question

Free PMP Exam Sample QuestionQuestion:

You are currently performing quality assurance on your project by conducting a Quality Audit. Which of the following is not an objective of a Quality Audit?

A. Share the good practices introduced or implemented in similar projects in the organization and/or industry
B. Document the effectiveness of the Risk Management process
C. Identify all the good/best practices being implemented
D. Identify all the gaps/shortcomings

-------------------------

Hint: Think about the specific knowledge area in which you conduct the Perform Quality Assurance process.

-------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

Answer and Explanation:

The Correct Answer is B.

The Perform Quality Assurance process is conducted in the Quality Management knowledge area, not the Risk Management knowledge area. Although documenting the effectiveness of the Risk Management process is an important activity, it is performed in the Risk Management knowledge area, not the Quality Management area. All remaining answer choices are specific objectives of the Quality Audit.

 