Free PMP Exam Sample Question

Free PMP Exam Sample QuestionThe following PMP® exam sample question is taken from the Free PMP Exam Simulator (The answer is at the very bottom):

------------------------------

You are managing a construction project. You have just finished defining your activities and you are now estimating their durations. Obtaining government permits is one of the project activities that is critical to the success of your project. You obtain expert opinion regarding time requirements for this activity, and you have determined that the duration will most likely be 15 days. It would be very optimistic to expect to obtain the permits in 10 days. In addition, taking the current environmental factors into consideration, it may take up to 30 days to obtain the permits. What estimate should you use for this activity if you want to put more weight on the most likely duration with a further 10 percent contingency reserve? (Round to the nearest day.)

A) 17 Days
B) 18 Days
C) 20 Days
D) 33 Days

------------------------------

Hint: Use the PERT formula to determine your initial estimate.

------------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

Answer and Explanation:
The Correct Answer is B. As you want to put more weight on the most likely estimate, you should use the PERT formula for your initial estimate rather than taking a simple average of the three values. Your PERT estimate will be (10 + 4*15 + 30) / 6 = 16.67 days. Adding a 10 percent contingency reserve to it will give 16.67*1.1 = 18.33 days. Rounding your estimate to the nearest day will give 18 days.

 