Free PMP Exam Sample Question

Free PMP Exam Sample QuestionThe following PMP® exam sample question is taken from the Free PMP Exam Simulator (The answer is at the very bottom):

------------------------------

One of the project managers at your company has resigned and you have been assigned as the new project manager for his old project. You call a team meeting to get a rundown on the project activities completed to date. The project team tells you that the project is in its planning stage. The team also tells you that after creating the Project Charter and the Stakeholder Register, they finished creating the Requirements Management Plan, the Requirements Documentation, and the Requirements Traceability Matrix. They are now working on the project Work Breakdown Structure (WBS). What has the project team forgotten to do?

A) Create the Scope Statement before creating the WBS
B) Create the Project Management Plan before creating the Requirements Management Plan
C) Create the project Statement of Work before creating the Project Charter
D) Create the project templates before starting the Planning processes

------------------------------
 Hint: Which PMBOK process has the team forgotten to perform?
 ------------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

Answer and Explanation:
The Correct answer is A. Project templates are not created as a part of any of the project management processes. These can be found in the Organizational Process Assets. The Project Management Plan cannot be finalized until all of the project planning processes are finished, making that choice also incorrect. The Statement of Work is provided either by the project sponsor or the customer and is not created by the project team, so that choice is incorrect as well. As the team has moved on to creating the WBS, they have forgotten to create the Project Scope Statement, which is always created before the WBS.