You are managing the construction of your company's new office building. Your project sponsor approaches you and asks you to email him a project document that you presented to senior management during your last project status meeting. He tells you that he has forgotten the name of the document you mentioned during your presentation. However, he said that it contained a textual description of each of the project requirements, the rationale for their inclusion, respective owner, source, priority, and the current status. Which project document is your project sponsor requesting?

A) The Requirements Management Plan
B) The Requirements Traceability Matrix
C) The Work Breakdown Structure
D) The Resource Breakdown Structure

------------------------------
 
Hint: The project sponsor is referring to a document you presented to senior management during your last status meeting.
 
------------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

Answer and Explanation:
The Correct answer is B: Your project sponsor is referring to the Requirements Traceability Matrix as this contains all of the information given in this scenario. None of the other project documents listed as answer choices links requirements to their origin and traces them throughout the Project Life Cycle. Typical attributes used in the requirements traceability matrix include a unique identifier, a textual description of the requirement, the rationale for inclusion, owner, source, priority, version, current status (e.g. active, cancelled, deferred, added, approved), and date completed.