Free PMP Exam Sample Question

Free PMP Exam Sample QuestionThe following PMP® exam sample question is taken from the Free PMP Exam Simulator (The answer is at the very bottom):

------------------------------

A project manager has been asked to document the product development process. Which of the following tools should the manager use?

A) Fishbone diagram
B) Pareto diagram
C) Flow charts
D) Ishikawa diagram

------------------------------

Hint: These shows how various elements of a system or a process interrelate.

------------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

Answer and Explanation:
The Correct Asnwer is C.The flow chart shows how various elements of a system or a process interrelate.

Print Email