Free PMP Exam Sample Question

Quiz Depositphotos 6241386 xsThe following PMP® exam sample question is taken from the Free PMP Exam Simulator (The answer is at the very bottom):

------------------------------

The total actual cost incurred in accomplishing a task on the schedule activity is $650 and the earned value on the schedule activity is $900. What would the cost performance index indicate?

A) Cost overruns
B) Cost underrun
C) Cost as per estimation
D) Project progress

------------------------------
Hint: CPI = EV / AC
------------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

Answer and Explanation:
The Correct Answer is B. CPI=EV/AC, EV = 900, AC = 650. Therefore, CPI = 1.38. CPI > 1 indicates cost underrun.

Print Email