A project manager is making a quantitative assessment of the probable cost of the resources required to complete the schedule activities. He considers inflation allowance and a special cost contingency reserve. Which type of estimation is this an example of?_x000D_

A) Parametric Estimation
B) Activity Cost estimation
C) Cost aggregation
D) Funding Limit Reconciliation

------------------------------
Hint: The PM is determining the activity costs and contingency reserve requirements.
------------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

Answer and Explanation:
The Correct Answer is B. The PM is determining the activity costs and contingency reserve requirements.This is a part of the Estimate Costs process.