Free PMP Exam Sample Question

Free PMP Exam Sample QuestionThe following PMP® exam sample question is taken from the Free PMP Exam Simulator (The answer is at the very bottom):

------------------------------

Which of the following tasks will not be done by the processes in the planning process group?

A) Define and refine objectives
B) Plan the course of action required to attain the objectives.
C) Identify the project scope
D) Integrate people and other resources to carry out the project management plan for the project

------------------------------
Hint: What is the function of the Direct and Manage Project Work process?
------------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

Answer and Explanation:
The Correct Answer is D. Integrating resources is the task of the Direct and Manage Project Work process that belongs to the executing process group.