Free PMP Exam Sample Question

The following PMP® exam sample question is taken from the Free PMP Exam Simulator:

------------------------------

You are managing a water supply network deployment project. During project planning you are considering two approaches to lay the pipe network. Approach A will most likely cost $50,000 (±5%). Approach B will most likely cost $25,000 (±40%). Which approach will you select if your project stakeholders' risk tolerances are low and if you want to select the less risky approach?

A) Neither approach since they are not definitive estimates.
B) Approach B since it ranges from $15,000 to $35,000.
C) Approach A since it ranges from $47,500 to $52,500.
D) A combination of approach A and B.

------------------------------
Hint: Estimates are never definitive.
------------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

The correct answer is C.
Explanation: Please note that the question doesn't ask for the approach that is more financially feasible. Instead, the question asks you to identify the approach that has the lower risk. The larger the range of an estimate, the larger the risk. Since approach B is a wide range estimate, it is more risky. Approach C has a narrow estimate, which makes this approach less risky.

Print Email