Free PMP Exam Sample Question

The following PMP® Exam Sample Question is taken from the Free PMP Exam Simulator:

------------------------------

You are managing a software development project. You want to create the basis that will be used later on for estimating, scheduling, executing, monitoring, and controlling the project work. Which process performs this activity?
 
a) Create WBS
b) Define Scope
c) Define Activities
d) Create Project Management Plan
 
------------------------------

Hint: Estimating is performed when the activities are defined and the schedule is prepared.

-----------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

ANSWER AND EXPLANATION:
The correct answer is C.
Explanation: Activities form a basis for estimating, scheduling, executing, and monitoring and controlling the project work. This is performed in the Define Activities process.