Free PMP Exam Sample Question

The following PMP® exam sample question is taken from the Free PMP Exam Simulator:

------------------------------

You are using Microsoft Project as a tool to manage the project. All the activities have been recorded and the Work Breakdown Structure has been prepared. Your project team wants to use different units of work for different resources. Which document establishes the information regarding units of measurement for resources on a project?

A.) Enterprise Environmental Factors
B.) Cost Management Plan
C.) Project Charter
D.) Performance Measurement Documents

------------------------------

Hint: Units of measurement is contained in one of the Project Management Plan’ subsidiary plans.

-----------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

ANSWER AND EXPLANATION:
The correct answer is B
Explanation: The Cost Management Plan establishes units of measurement such as staff hours, staff days, and staff weeks.
Reference: PMBOK® Guide 4th Edition, page 166