Free PMP Exam Sample Question
The following PMP® exam sample question is taken from the Free PMP Exam Simulator:
------------------------------
B.) Escalate to the project team.
C.) Perform the Plan Risk Responses process again.
D.) Escalate to the sponsor.
------------------------------
Hint: If the primary risk response plan fails, there should be one more plan to use as a reaction to a risk.
-----------------------------
Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.
(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)
ANSWER AND EXPLANATION:
The correct answer is A
Explanation: A Fallback Plan is used when a contingency plan is not effective.
Reference: PMBOK® Guide 4th Edition, page 306