Free PMP Exam Sample Question

The following PMP® exam sample question is taken from the Free PMP Exam Simulator:

------------------------------

You planned for Contingency Reserves for your office building construction project and used contingency plans to control risks. However, your attempts to control project risks were not effective. What is the next step you should take?
 
A.) Use a Fallback Plan.
B.) Escalate to the project team.
C.) Perform the Plan Risk Responses process again.
D.) Escalate to the sponsor.

------------------------------

Hint: If the primary risk response plan fails, there should be one more plan to use as a reaction to a risk.

-----------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

ANSWER AND EXPLANATION:
The correct answer is A
Explanation: A Fallback Plan is used when a contingency plan is not effective.
Reference: PMBOK® Guide 4th Edition, page 306