According to the PMBOK® Guide , a WBS is not directly involved in which of the following processes?

A.) Develop Project Management Plan
B.) Define Activities
C.) Create WBS
D.) Define Scope

------------------------------

Hint: The Develop Project Management Plan process creates the Scope Management Plan.

-----------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

ANSWER AND EXPLANATION:
The correct answer is D
Explanation: The Develop Project Management Plan process carries out scope planning, which documents how the WBS will be created and defined. Define Activities takes the WBS as an input and decomposes it to define activities. Create WBS creates the WBS itself. The Define Scope process must be completed before the Create WBS process can be started.
Reference: PMI Practice Standard for WBS 2nd Edition, page 14