Free PMP Exam Sample Question

The following PMP® exam sample question is taken from the Free PMP Exam Simulator:

------------------------------

Which of the following Enterprise Environmental Factors does not influence the Estimate Activity Durations process?

A.) Duration Estimating Databases
B.) Project Management Information Systems
C.) Productivity Metrics
D.) Published Commercial Information

------------------------------
Hint: All of the given choices are valid Enterprise Environmental Factors but which one of them is not relevant to the Estimate Activity Durations process?

------------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

ANSWER AND EXPLANATION:
The correct answer is B
Explanation: All of the given choices are valid Enterprise Environmental Factors. However, the Project Management Information System will not influence the Estimate Activity Durations process. We do use project management software for scheduling (Scheduling Tools) during the Estimate Activity Durations process but we do not use the Project Management Information System. Conceptually, these two software applications are different and perform different functions. However, you can find a software application that performs both of these functions, e.g., Microsoft Project. For the actual PMP Exam you must remember that these two software applications are different and perform different functions, i.e., one is for reporting and one is for scheduling.
Reference: PMBOK® Guide 4th Edition, page 148