Free PMP Exam Sample Question

The following PMP® exam sample question is taken from the Free PMP Exam Simulator:

------------------------------

Your pharmaceutical drug manufacturing project is running late and you have deadlines to meet on your project.You want to replace some of the inefficient human resources with more talented human resources to finish the project on time. What risk response strategy is being followed in this context?

A.) Share
B.) Accept
C.) Transfer
D.) Mitigate

------------------------------
Hint: You are trying to reduce the likelihood of the risk occurrence.

------------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

ANSWER AND EXPLANATION:
The correct answer is D
Explanation: This is an example of Risk Mitigation. By replacing the human resources you are reducing the probability of the risk
Reference: PMBOK® Guide 4th Edition, page 304