Free PMP Exam Sample Question

The following PMP® exam sample question is taken from the Free PMP Exam Simulator at http://free.pm-exam-simulator.com - The answer is at the very bottom:

------------------------------

Your Risk Register says if your IT Administrator is unavailable for a period longer than a week it will cause serious issues for your project. You have just learned from you Human Resource Department that your IT Administrator has resigned and has given a one-month notice for the company to find a replacement.
This situation is an example of which of the following:

A.) Secondary Risk
B.) Residual Risk
C.) Contingency Plan
D.) Trigger

------------------------------

Hint: You have found out that a risk is about to occur.

------------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

ANSWER AND EXPLANATION:
The correct answer is D
Explanation: Since you have just discovered that one of your project's identified risk is about to happen, this is an example of a Risk Trigger.
Reference: PMBOK® Guide 4th Edition, page 306