____________ is the total cost to produce the product or service of the project while meeting the quality standards plus the operating cost.

A.) Total Cost of Ownership
B.) Estimated Cost
C.) Cost of Quality
D.) Budgeted Cost

------------------------------

Hint: What is the total cost of a product?

------------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

ANSWER AND EXPLANATION:
The correct answer is A
Explanation: Total Cost of Ownership is the total cost of a product including the development cost, quality activities cost, and operating costs. Cost of Quality means the Cost of Quality activities only. Neither Budgeted Cost nor Estimated Cost are the actual costs to produce the product.
Reference: PMBOK® Guide 4th Edition, page 327