You have just been assigned as the project manager for a new construction project. The Project Charter has been handed over to you by your sponsor authorizing you as the project manager. You have performed the Stakeholder Analysis process and documented the information in the Stakeholder Register. Which of the following processes should be performed next?

A.) Plan Communications
B.) Define Activities
C.) Determine Budget
D.) Create WBS

------------------------------
Hint: Follow the PMBOK® Guide recommended sequence.
------------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

ANSWER AND EXPLANATION:
The correct answer is A
Explanation: According to the scenario, you have just completed the project initiation phase, in particular you have completed the Identify Stakeholders process. You should now perform the Plan Communications, which follows after identify stakeholders.
Reference: PMBOK® Guide 4th Edition, page 247