The Six Sigma process uses which of the following quality cycles?
A.) Plan-Do-Check-Act
B.) Plan-Perform-Verify-Act
C.) Plan-Execute-Monitor-Run
D.) Plan-Do-Control-Act
------------------------------
Hint: Deming proposed this quality cycle.
------------------------------
Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.
(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)
ANSWER AND EXPLANATION:
The correct answer is A
Explanation: The Plan-Do-Check-Act cycle was proposed by Deming, which uses Six Sigma processes.