Free PMP Exam Sample Question

The following PMP® exam sample question is taken from the Free PMP Exam Simulator at http://free.pm-exam-simulator.com - The answer is at the very bottom:

------------------------------

You are developing your project’s Human Resource Plan. Your sponsor asked you to take the historical information from previous projects to determination the project’s human resource roles and responsibilities. Which of the following sources contains this information?

A.) Organizational Process Assets
B.) Enterprise Environmental Factors
C.) Project Management Plan
D.) Project Charter

------------------------------

Hint: Look for the keyword phrase 'historical information'. Only one of these options contains historical information.

------------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

ANSWER AND EXPLANATION:
The correct answer is A
Explanation: Organizational Process Assets contain historical information about previous projects.
Reference: PMBOK® Guide 4th Edition, page 219