Free PMP Exam Sample Question

Quiz Depositphotos 6241386 xsThe following PMP® exam sample question is taken from the Free PMP Exam Simulator at http://free.pm-exam-simulator.com - The answer is at the very bottom:

------------------------------

The type, quantities and assumptions made in determining the resources, basis of estimate for each resource, and availability of resources for each activity or work package is identified in which of the following documents?

A.) Resource Breakdown Structure
B.) Responsibility Assignment Matrix
C.) Resource Calendars
D.) Activity Resource Requirements

------------------------------

Hint: Carefully read the question. The question is asking for assumptions made in determining the resources, as well as the basis of estimates. This happens in the Estimate Activity Resources process. Think about the outputs of this process.

------------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

ANSWER AND EXPLANATION:
The correct answer is D
Explanation: The type, quantities and assumptions made in determining the resources, basis of estimate for each resource, and availability of resources for each activity or work package is identified in the Estimate Activity Resources process. Resource Calendars identify only type, quantity, availability, and capabilities of resources.
Reference: PMBOK® Guide 4th Edition, page 145