Free PMP Exam Sample Question

Free PMP Exam Sample QuestionThe following PMP® exam sample question is taken from the Free PMP Exam Simulator at http://free.pm-exam-simulator.com - The answer is at the very bottom:

------------------------------

The risk shared between the buyer and the seller is determined by which of the following?
A.) The Scope of Work
B.) The Teaming Agreement
C.) The Contract Type
D.) The Project Charter

------------------------------

Hint: How can you control the project risk while negotiating the scope of work with a seller??

------------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

ANSWER AND EXPLANATION:
The correct answer is C
Explanation: For example, fixed-price contracts have a higher risk for the seller while cost-reimbursable contracts have a higher risk for the buyer.
PMBOK® Guide 4th Edition, page 322