Project Integration Management consists of all of the following activities except?
A.) Develop Project Charter
B.) Develop Project Management Plan
C.) Perform Integrated Change Control
D.) Collect Requirements
------------------------------
Hint: Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate various processes and activities.
------------------------------
Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.
(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)
ANSWER AND EXPLANATION:
The correct answer is D
Explanation: Collect Requirements is not a process in Project Integration Management. This process is contained in Project Scope Management.
Reference: PMBOK® Guide 4th Edition, page 7