Free PMP Exam Sample Question

All,

The following PMP® exam sample question is taken from https://free.pm-exam-simulator.com - The answer is at the very bottom:

------------------------------

Question: You are managing a construction project. You have just been intimated that it is likely to rain heavily during the next week. This can delay your project by a week and you will miss a deadline. This risk will cost you a potential impact of $50,000 if it happens. The probability of the occurrence of this risk is 75%. What is the expected value for this risk?

A. 37500

B. -37500

C. 50000

D. -50000

Hint: Calculate the expected value by EMV formula. Also note that threats are treated as negative numbers.

------------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

Explanation: EMV for a risk is calculated by multiplying the value of its impact by its probability of occurrence. This will result in 75% * -$50,000 = -$37,500.

 

The Correct Answer is B.