Free PMP Exam Sample Question
The following PMP® exam sample question is taken from http://www.free-pm-exam-questions.com - The answer is at the very bottom:
------------------------------
Who determines which processes from the process group will be employed to achieve
the desired objective?
A) The CEO
B) The most senior project team member.
C) Project manager & the project team
D) A project initiator external to the project organization
------------------------------
Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.
(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)
The Correct Answer is C.