Free PMP Exam Sample Question

The following PMP® exam sample question is taken from http://www.free-pm-exam-questions.com - The answer is at the very bottom:


------------------------------

Who determines which processes from the process group will be employed to achieve

the desired objective?

A) The CEO

B) The most senior project team member.

C) Project manager & the project team

D) A project initiator external to the project organization

------------------------------

All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try it for 3 days. We are a PMI Registered Education Provider. The Correct Answer is C.