The following PMP® exam sample question is taken from http://www.free-pm-exam-questions.com – The answer is at the very bottom:

—————————-

PMBOK Section: Estimate Activity Durations
Process Group: Planning Process Group
Question Type: Calculation
Knowledge Area: Time Management
Difficulty Level: Moderate

Question: "You are managing a construction project. You are currently estimating the duration of a very critical activity. You have gathered the following information from the experts:

Best case scenario: Activity can take 3 days to complete.
Worst case scenario: Activity may take up to 12 days to complete.
Expected scenario: On average it takes up to 6 days to complete such activities.

What duration you will put into your schedule for this activity if you want to put some weight on the expected scenario?"

A. 7 days
B. 7.5 days
C. 6 days
D. 6.5 days

Hint : Use PERT to calculate.
Reference: PMBOK4 – pg:150
—————————-

All our free questions are updated to the latest PMBOK® Guide standard. Stop by at: http://www.free-pm-exam-questions.com here to receive the questions via email. We are a PMI Registered Education Provider.

Explanation:Since you want to put some weight on the expected scenario, you will use the PERT formula. Your estimate will then be 6.5 days. Hence choice D is the correct answer.

Comments Disabled

Commenting has been disabled because we are receiving too much spam. Please send your questions & comments to This email address is being protected from spambots. You need JavaScript enabled to view it.

Cornelius Fichtner, PMP

Project manager, PMP trainer, host of The PM Podcast, public speaker and gummi bear addict.