Free PMP Exam Sample Question

The following PMP® exam sample question is taken from http://www.free-pm-exam-questions.com

----------------------------
PMBOK Section:    Sequence Activities  
Process Group:    Planning  Process Group   
Question Type:    Calculation  
Knowledge Area:   Time Management   
Difficulty Level: Moderate


Question: "Activity / Duration / Predecessor

A / 2 / Start
B / 4 / A,E
C / 6 / A
D / 3 / B,C
E / 7 / Start
F / 2 / E

What is the critical path?"          

A. Start-A-B-D-End        
B. Start-E-F-End         
C. Start-A-C-D-End        
D. Start-E-B-D-End                    

Hint : Use PDM to calculate.       
Reference: PMBOK4 - pg:138                   

----------------------------

All our free questions are updated to the latest PMBOK® Guide standard. Sign up here to receive the questions via email. We are a PMI Registered Education Provider.

The correct answer is D.
Explanation: The critical path of the data given is Start-E-B-D-End. Hence choice D is correct, while rest of the choices is incorrect.

Comments Disabled

Commenting has been disabled because we are receiving too much spam. Please send your questions & comments to This email address is being protected from spambots. You need JavaScript enabled to view it.

Cornelius Fichtner, PMP

Project manager, PMP trainer, host of The PM Podcast, public speaker and gummi bear addict.